Schedule:

Major Goal Dates:

6/11: Finish actuator design and programming approach.

6/25: Have chosen a economical motor that has enough torque to flex the copper and enough speed to achieve the desired effect.

7/9: Be finished at least one row and have the materials for the rest.

7/16: Assemble the rest of the rows.

7/23: Integrate the components that interact with the viewer(s).